arcodangeandClaude Fable 5 5430e5f3ac docs(prd): dated roadmap leaf — Gantt, milestone spine, re-baselining rule
New roadmap.md: mermaid Gantt (validated) putting the six phases on
calendar time from baseline 2026-07-11 — P2 e-invoicing opens the plan
(ADR D4 target 08-14, two-week fallback before the hard 09-01), P1
flagship in parallel (golden set first, A2 earned ~10-09), ledger-
compliance verifications early September (FY-2026 FEC depends on the
accounting-module answer), P3 standing fleet through autumn (sentinel
24/7 ~11-13), P4 money-loop exit over December, P5 riding the fiscal
calendar (acompte 12-15, CA3 switch 01-01, Q1 filing April, CA12 early
May, AG 06-30), P6 e-reporting proven months before 2027-09-01.
Immovable-milestone table, dependency notes, re-baselining rule
(engineering bars slide, diamonds don't — slips shed scope instead).
Wired: hub pointer + leaves row, poc-plan/STATUS backlinks.

Co-Authored-By: Claude Fable 5 <[email protected]>
2026-07-11 15:02:02 +02:00

105 lines
8.1 KiB
Markdown
Raw Permalink Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
[vibe](../../README.md) > [PRD](../README.md) > [AI back-office](README.md) > **Roadmap**
# Roadmap — the dated execution plan
> **Status:** In design (baseline 2026-07-11)
> **Last Updated:** 2026-07-11
> **Up:** [AI back-office hub](README.md)
> **Related:** [POC plan](poc-plan.md) · [STATUS](STATUS.md) · [Compliance](compliance.md) · [Task inventory](task-inventory.md)
The [phases](README.md#phased-roadmap) put in calendar time. Two kinds of dates coexist and must never be confused: **fiscal/regulatory milestones are immovable** (diamonds, several marked critical); **engineering dates are planning anchors** for a solo operator working part-time on this (~12 focused days/week between billable work) — they re-baseline freely, the milestones don't move to accommodate them.
## Gantt
```mermaid
%%{init: {'theme':'base'}}%%
gantt
title AI back-office — implementation roadmap (baseline 2026-07-11)
dateFormat YYYY-MM-DD
axisFormat %b %y
section P2 · E-invoicing (hard 09-01)
POC-6 Qonto PA validation (reception + API pull) :crit, p6, 2026-07-13, 2026-08-14
ADR D4 merged (Qonto = PA) :milestone, crit, 2026-08-14, 0d
Fallback window (other PA if POC-6 fails) :p6b, 2026-08-17, 2026-08-28
E-invoice reception mandatory :milestone, crit, 2026-09-01, 0d
section P1 · Flagship pipeline
Golden set + injection fixtures :a1, 2026-07-13, 2026-07-24
POC-5 model routing bench :a2, 2026-07-22, 2026-08-07
POC-1 build (extract→validate→gate→promote→GED) :a3, 2026-07-27, 2026-09-11
POC-1 exit gate (10 real invoices, zero fixes) :a4, 2026-09-14, 2026-10-09
T02/T03 earn A2 :milestone, 2026-10-09, 0d
section Ledger compliance (sandbox-first)
Dolibarr verifications (compta module, FEC, BlockedLog, D7) :c1, 2026-09-07, 2026-09-25
Accounting-module chantier (conditional) :c2, 2026-10-01, 2026-11-27
First monthly T15 audit pack :milestone, 2026-11-02, 0d
section P3 · Standing fleet
ADRs D1 + D2 (queue, orchestration) :b1, 2026-09-14, 2026-09-25
Queue + digest + approval cards :b2, 2026-09-28, 2026-10-23
T13/T14 watchdogs (snapshot cron, backup freshness) :b3, 2026-09-28, 2026-10-09
T17 second-brain wiring :b4, 2026-10-12, 2026-10-23
POC-2 Pi sentinel (deploy + eval 200 mails) :b5, 2026-10-05, 2026-10-30
POC-2 soak (24/7, zero evictions) :b6, 2026-11-02, 2026-11-13
Sentinel live 24/7 :milestone, 2026-11-13, 0d
section P4 · Money loops
POC-3 build (weekly reco + payment recording) :d1, 2026-11-02, 2026-11-20
POC-3 exit (1 month, zero unexplained deltas) :d2, 2026-11-23, 2026-12-24
T05 client invoice A2 (D3) + dunning + cash report :d3, 2026-11-16, 2026-12-18
section P5 · Fiscal autopilot
Fiscal profile + calendar files + T11 reminders :e1, 2026-11-09, 2026-11-27
POC-4a dry-run acompte décembre :e2, 2026-11-30, 2026-12-11
Acompte TVA décembre :milestone, 2026-12-15, 0d
CA3 quarterly regime starts :milestone, crit, 2027-01-01, 0d
POC-4b CA3 Q1 simulation + expert checkpoint :e3, 2027-01-11, 2027-02-26
Prepare real CA3 2027-Q1 (T10) :e4, 2027-04-01, 2027-04-16
CA3 Q1 filing (April window) :milestone, 2027-04-20, 0d
Prepare CA12 FY2026 (credit recovery) :e5, 2027-04-19, 2027-05-03
CA12 FY2026 filing :milestone, 2027-05-04, 0d
AG — annual accounts approval :milestone, 2027-06-30, 0d
section P6 · Emission era
E-reporting pipeline (Dolibarr→PA) + emission readiness :f1, 2027-05-03, 2027-07-30
E-reporting + emission mandatory (PME) :milestone, crit, 2027-09-01, 0d
```
1. **Phase 2 opens the plan, not phase 1**: POC-6 (Qonto-as-PA validation) starts immediately and must merge its ADR by mid-August, leaving a two-week fallback window before the immovable **2026-09-01 reception mandate**.
2. **Phase 1 runs in parallel from day one**: the golden set is built first (it gates everything), POC-5 benches the four tiers on it, and POC-1 builds the flagship supplier-invoice pipeline through September; its exit gate then consumes ~a month of *real* invoice flow, earning T02/T03 their A2 around **mid-October**.
3. The **ledger-compliance verifications** run on sandbox checkpoints in September — early on purpose: if the double-entry accounting module needs enabling and mapping, the conditional chantier must finish well before FY-2026 close so the year's FEC is producible.
4. **Phase 3 assembles the standing fleet** through autumn — queue/digest/approval cards (settling D1D2), watchdogs, second-brain wiring, and the Pi sentinel with its two-week soak: 24/7 triage is live by **mid-November**.
5. **Phase 4 closes the money loop over December**: reconciliation + payment recording must survive one full calendar month with zero unexplained deltas — deliberately scheduled over a month that includes the December acompte and year-end activity.
6. **Phase 5 rides the fiscal calendar**: dry-run of the December acompte (first €-parity proof), the **CA3 regime switch on 2027-01-01**, a Q1 simulation validated by the expert-comptable checkpoint, then the first real CA3 (April) and the CA12 that recovers the accumulated TVA credit (early May), with the AG closing FY 2026 by end of June.
7. **Phase 6 prepares the 2027-09-01 mandate** from May, so e-reporting of the KM export invoices is proven months before it becomes law — mirroring the phase-2 pattern of landing early on a hard date.
## Milestones (the immovable spine)
| Date | Milestone | Nature |
| --- | --- | --- |
| 2026-08-14 | ADR D4 merged — Qonto confirmed as PA | engineering target (feeds a hard date) |
| **2026-09-01** | **E-invoice reception mandatory** | **regulatory — hard** |
| 2026-10-09 | T02/T03 earn A2 (flagship pipeline trusted) | engineering gate |
| 2026-11-02 | First monthly T15 audit pack | engineering gate |
| 2026-11-13 | Pi sentinel live 24/7 | engineering gate |
| 2026-12-15 | Acompte TVA de décembre (≈ 0 € expected — verify) | fiscal — hard |
| **2027-01-01** | **Régime simplifié abolished → quarterly CA3** | **regulatory — hard** |
| 2027-04-20 | First real CA3 (2027-Q1) filed | fiscal — hard (April window) |
| 2027-05-04 | CA12 FY-2026 filed (TVA credit recovery) | fiscal — hard (early-May window) |
| 2027-06-30 | AG — FY-2026 accounts approved | legal — hard |
| **2027-09-01** | **E-reporting + emission mandatory (PME)** | **regulatory — hard** |
## Dependencies that shape the plan
- **Golden set → everything**: no atom earns autonomy without it ([QA strategy](qa-strategy.md#golden-datasets)); hence it is the very first task.
- **POC-1 → POC-3**: payment recording reuses the manifest/gate/promote loop the flagship proves.
- **Compliance verifications → CA12/FEC**: the accounting-module question must be answered while there is still time to journalize FY 2026 ([compliance](compliance.md#dolibarr-verifications-sandbox-first)).
- **Queue + digest (P3) → every standing loop**: T15 audits, watchdogs and the sentinel report through the digest; that is why P3 sits between the flagship and the money loops.
- **POC-4a → POC-4b → real CA3**: each fiscal dry-run de-risks the next, and the expert checkpoint sits *before* the first real quarterly filing.
## Re-baselining rule
Slips are expected (solo operator, billable work first). The rule: **engineering bars may slide; diamond milestones may not** — a slip that threatens a hard milestone triggers scope-shedding on the engineering side (e.g. POC-6 falls back to manual PA reception, POC-1 stays at A1) rather than date-shifting. Actuals and slips are recorded in [STATUS](STATUS.md) as they happen; this page is re-dated only at phase boundaries so it stays a plan, not a diary.