New roadmap.md: mermaid Gantt (validated) putting the six phases on
calendar time from baseline 2026-07-11 — P2 e-invoicing opens the plan
(ADR D4 target 08-14, two-week fallback before the hard 09-01), P1
flagship in parallel (golden set first, A2 earned ~10-09), ledger-
compliance verifications early September (FY-2026 FEC depends on the
accounting-module answer), P3 standing fleet through autumn (sentinel
24/7 ~11-13), P4 money-loop exit over December, P5 riding the fiscal
calendar (acompte 12-15, CA3 switch 01-01, Q1 filing April, CA12 early
May, AG 06-30), P6 e-reporting proven months before 2027-09-01.
Immovable-milestone table, dependency notes, re-baselining rule
(engineering bars slide, diamonds don't — slips shed scope instead).
Wired: hub pointer + leaves row, poc-plan/STATUS backlinks.
Co-Authored-By: Claude Fable 5 <[email protected]>
The PARA Obsidian vault (arcodange/SecondBrain — git-synced, sb.py
digest/inbox/gitea-ingest jobs on the hermes cron ticker, local Ornith
model, mcp-obsidian access) enters the PRD as a first-class component:
new T17 knowledge capture & retrieval fiche, knowledge-layer section in
the architecture (ERP = book of record, vault = context + institutional
memory, append-only idempotent deposits, trusted-but-stale retrieval),
hermes/Ornith recognized as the resident M4 runtime (D2 leaning, new D7
cluster<->vault access decision), foundation ledger row, diagram +
goals updated (mermaid revalidated, 231 links/anchors re-checked green).
Co-Authored-By: Claude Fable 5 <[email protected]>
New PRD tree vibe/PRD/ai-back-office/ (hub + 6 leaves + STATUS): task
inventory T01-T16 with mode operatoire, atom/contract architecture on
the ADR-0003 write gate, four-tier model fleet (Claude/Mistral/M4/Pi),
12 challenges with mitigations, POC plan with exit criteria, QA
strategy with autonomy promotion gates. Index row + bidirectional
backlinks (erp guidebook, safe-prod PRD).
Co-Authored-By: Claude Fable 5 <[email protected]>