arcodangeandClaude Fable 5 5430e5f3ac docs(prd): dated roadmap leaf — Gantt, milestone spine, re-baselining rule
New roadmap.md: mermaid Gantt (validated) putting the six phases on
calendar time from baseline 2026-07-11 — P2 e-invoicing opens the plan
(ADR D4 target 08-14, two-week fallback before the hard 09-01), P1
flagship in parallel (golden set first, A2 earned ~10-09), ledger-
compliance verifications early September (FY-2026 FEC depends on the
accounting-module answer), P3 standing fleet through autumn (sentinel
24/7 ~11-13), P4 money-loop exit over December, P5 riding the fiscal
calendar (acompte 12-15, CA3 switch 01-01, Q1 filing April, CA12 early
May, AG 06-30), P6 e-reporting proven months before 2027-09-01.
Immovable-milestone table, dependency notes, re-baselining rule
(engineering bars slide, diamonds don't — slips shed scope instead).
Wired: hub pointer + leaves row, poc-plan/STATUS backlinks.